Administrative Modifications to the Evansville MPO FY 2010 - 2013 TIP 
         
Date DES/Item# Project Description Text Change  Prior Status/Change
3/16/2010 0300578 Intersection realignment project at Plum St., Main St. and Jennnings FY 2010 CN 509,803 HES/HSIP FY 2010 CN  460,000 HES
    St. in Newburgh.  Revise project budget. 5,534 LOCAL 18,000 LOCAL
3/25/2010 02-2040.00 Audubon Parkway - Repair and grind pavement from 0.178 mi. FY 2010 PE 300,000 FS2 Add PE to TIP
    W. of KY 6110 to Daviess County line.  Add design funding    
3/29/2010 02-2040.00 Audubon Parkway - Repair and grind pavement from 0.178 mi. FY 2010 PE 300,000 NHS FY 2010 PE 300,000 FS2
    W. of KY 6110 to Daviess County line.  Change design funding     
4/19/2010 9903240 US 41 - Road reconstruction from 0.2 mi. N of S jct. with SR 66 FY 2010 PE 31,200 NHS FY 2010-12 PE 229,000 NHS
to 0.4 mi. S of N jct. with SR 66.  Revise cost and schedule to split  7,800 INDOT 45,800 INDOT
single phase project into two phases FY 2010 ROW 128,000 NHS FY 2012 ROW 128,000 NHS
Note:  Original limits were Eagle Creek Slough to  0.3 mi. S of  32,000 INDOT 32,000 INDOT
SR 66 FY 2010 CN 8,000,000 NHS FY 2013 CN 26,240,000 NHS
  2,000,000 INDOT 6,560,000 INDOT
4/19/2010 1000069 US 41 - Road reconstruction from Eagle Creek Slough to 0.2 mi. S FY 2012 PE 32,000 NHS See above - Add Second Phase
of S jct. with SR 66.  Revise cost and schedule to split single 8,000 INDOT
 phase project into two phases FY 2013 CN 18,240,000 NHS
  4,560,000 INDOT
7/30/2010 1005569 Interlake Multi-Use Recreation Area: FY 2011 PE 40,000  RTP FY 2011 CN 655,392  RTP
DNR project to develop multi-use recreational park at Interlake, a  10,000DNR 163,848 DNR
3500 acre property near Lynnville in Warrick County.   Revise cost FY 2011 CN 615,392  RTP  
to include PE funding 153,848 DNR